$12.5M Rangeville Church, St1 completed
Stage 1 of the Rangeville Community Church has reached completion on the corner of MacKenzie and Stenner Streets, Toowoomba. This article provides progressive images of its construction.
StruXi was the Project Superintendent. McNab Developments (Qld) Pty Ltd was the Builder.
(Our website also presents a case study of this community icon.)
- 28/03/11 – Standing at mezzanine overlooking Youth Hall Auditorium
- 28/03/11 – Entry Lobby and Foyer circulation zone
- 28/03/11 – Welcome to the new Rangeville Community Church premises
- 23/03/11 – Shadesails to playground area
- 23/03/11 – Lower carparks and landscaping with acoustic fence
- 14/03/11 – Balancing aircon in Multi Purpose Rooms
- 14/03/11 – Fitoff of a full commercial kitchen
- 08/03/11 – Fitoff of Toilets
- 28/02/11 – Front Facade
- 21/02/11 – Joinery to A0.51 Waiting Area
- 14/02/11 – Roadworks / carparks under construction
- 07/02/11 – Ceiling tiles to Lobby / Foyer
- 31/01/11 – Mezzanine view overlooking Youth hall / Stage
- 24/01/11 – Sports Floor to Youth Hall Auditorium
- 24/01/11 – Concrete roadworks leading to front Portico
- 14/01/11 – Multi Purpose Rms, rollers shutters to storage rooms
- 20/12/10 – Kerbs to roads
- 13/12/10 – Paint to offices corridor
- 06/12/10 – Installed glazed bi-fold doors to Multi Purpose Rooms
- 29/11/10 – Glazing to Lobby’s North facade
- 27/11/10 – Aerial view, looking East
- 22/11/10 – Lobby / Foyer curved ceiling grid
- 15/11/10 – Youth Hall airconditioning and wall linings
- 15/11/10 – Carparking and pathways to the south
- 08/11/10 – Wall linings, inspecting rooms A0.50 Open Office & A0.40 Pastor Office
- 08/11/10 – Front & Back facades; Ergon has arrived.
- 01/11/10 – Aerial view looking North (future Stage 2 outlined)
- 01/11/10 – Airconditioning to Lobby / Foyer
- 25/10/10 – Brickwork veneer for rendering
- 18/10/10 – External ramp construction
- 15/10/10 – Upper acoustic ceiling to Youth Hall
- 15/10/10 – Glazing commenced (windows to Multi Purpose Rms)
- 04/10/10 – Blockwork to 2nd zone of Multi Purpose Rooms
- 04/10/10 – Civil works in widening off-street carparking
- 27/09/10 – Services rough-in & blockwork to Youth Hall
- 27/09/10 – From the oval, looking South
- 20/09/10 – Roof trusses continue, multi purpose rooms adj Youth Hall
- 16/09/10 – Roof trusses erection to multi purpose rooms
- 13/09/10 – Paint to Youth hall, Blockwork to Ministry rooms
- 12/09/10 – Aerial view, looking North
- 06/09/10 – Inside the Youth Hall Auditorium
- 06/09/10 – Wall frames continue
- 30/08/10 – Blockwork & wall frames to multi purpose rms and boardroom zone
- 30/08/10 – Finishing concrete slab to Lobby
- 25/08/10 – Roof sheeting being loaded onto Lobby roof
- 16/08/10 – Ground slabs completed to Multi Purpose Rooms and Offices
- 09/08/10 – Portico front entrance takes shape
- 09/08/10 – Multi Purpose Rm slab poured (Youth Hall Auditorium in backgnd)
- 09/08/10 – Structural Steel to the Lobby roof
- 02/08/10 – Structural steel starts to Youth Hall Auditorium
- 26/07/10 – Blockwork, Boardroom and toilets (left), Offices (right)
- 19/07/10 – View through foyer to Picnic Point
- 16/07/10 – Erection of the Stage 1 tilt panels
- 12/07/10 – Tilt panels cast, awaiting erection
- 06/07/10 – Inground plumbing pipes and footings continue
- 28/06/10 – Casting the Stage 1 tilt panels
- 18/06/10 – 3x 95,000ltr ea inground tanks
- 18/06/10 – Bored Piers and Footings in background, Casting beds for tilt panels in foreground
- 15/06/10 – Building pad completed and boxing out of roads
- 31/05/10 – Clearing topsoil to building footprint
- 13/05/10 – A vacant, green fields site