Excitment is building for the new 7 Eleven service station that is coming to 85 Perth Street Toowoomba. The facility is totally new, having demolished the old service station, even replacing the old fuel tanks for new ones.
StruXi was successful in securing the key roles for Principal (lead) Consultant, Building Designer and Project Manager (Superintendent) from the concept stage all the way through to the end of construction.
The builder is Beech Constructions Pty Ltd, with proven experience in service station builds.
Below are some images taken during construction.
- 10/11/11 – 7-Eleven opens
- 10/11/11 – Service Station starts trading
- 28/10/11 – Ready for tenant fitout
- 06/10/11 – 7eleven signage
- 04/10/11 – Street view, nearing completion
- 26/09/11 – Concrete slabs and Shopfronts
- 25/08/11 – Fuel system installation
- 27/07/11 – Canopy steel erected
- 08/07/11 – Overview of site
- 08/07/11 – New fuel tanks and turrets installed
- 08/07/11 – Tilt panels erected
- 02/06/11 – Arrival of new fuel tanks
- 06/05/11 – Removal of old fuel tanks
- 05/05/11 – Demolition of old fuel station
- Not possible from this store
- 7-eleven logo